Click
here to view an Adobe Acrobat Reader version of this document
Implementation of the 2020 Transportation Plan
will require significant cooperation and coordination from the various
implementing agencies and will involve a combination of planning,
engineering, and construction activities. While construction of some
of the recommended projects is critical in the near future,
construction of other projects will be needed closer to the 2020
horizon year of the plan. In either case, it should be recognized that
new highway or transit projects require a considerable expenditure of
time and money to prepare the required project documents and plans.
Land acquisition alone typically takes a minimum of two years to
accomplish, and if eminent domain proceedings are initiated, a
five-year process is not unusual.
Table 19 and Table
20 summarize the recommended plan roadway projects, their
approximate limits, the type of improvements, and the estimated total
cost and cost by roadway jurisdiction. It should be noted that for
purposes of developing the long-range plan, planning-based cost
estimates were used, and therefore actual project costs may vary from
these figures once a project proceeds to the preliminary engineering
stage.
Project Staging Strategy
The transportation plan staging strategy assumes
that the requisite planning studies and engineering plans will occur
in the early years to ensure that the proposed projects are
incorporated into new development. The strategy also assumes that
corridor plans for those regional roadways and transit improvements
that are proposed to be improved will continue to be performed, such
as the plans that have been developed for the I-80 corridor, Strategic
Regional Arterials, Metra commuter rail major investment studies
(MIS), and others. These corridor plans would integrate transportation
and land use recommendations, and whenever possible, these
improvements would be included in the regional road and transit
construction projects.
The projects recommended in the transportation
plan must have a level of priority identified in order to focus on the
most immediate needs to be implemented first. To select projects for
the first stage of implementation, the various individual
characteristics of each improvement have been evaluated with regard to
several alternative strategies.
A strategy singles out or gives emphasis to one
objective. Each project is evaluated as to whether it would mostly
satisfy that objective. For example, providing more traffic capacity
on highly congested facilities could be the emphasis of a strategy.
Projects that significantly increase traffic capacity would be ranked
high and possibly included in the earlier stages of the overall
program.
Using this process, five alternative strategies
are suggested that define a priority by which roadway projects are
evaluated for staging purposes. The strategies are:
- Encourage development in specific,
established areas, as guided by the Land Resource Management Plan,
including the west edges of Bolingbrook and Romeoville, western
Joliet, Des Plaines River Valley, Frankfort/Mokena/New Lenox area,
and western University Park (I-57 corridor).
- Eliminate peak-hour traffic capacity
deficiencies and bottlenecks on congested facilities by making
selected capacity improvements.
- Avoid land use disruptions and property
takings, whenever possible, as traffic capacity is added in
developed areas, particularly downtowns.
- Protect right-of-way opportunities and fill
in the arterial street system.
- Support new development in the extended I-355
corridor (I-80 to Indiana state line), including land uses that
would benefit from the proximity of freeway access such as
distribution/warehousing facilities and highway-oriented
commercial uses.
Project Evaluations
Each project listed in Tables 19 and
20 was
evaluated with respect to the five strategies cited above. A
four-scale ranking system was used in the evaluation process:
- Indicates project substantially
achieves the strategy.
- Indicates some or modest
achievement.
- Indicates only small or little
achievement.
- Indicates no achievement.
The intent of the evaluation is to identify
those projects that tend to support all strategies. These would
satisfy any priority and should be highly ranked projects.
All projects will not perform equally well for
all strategies. The propensity for a project to rank high (i.e., how
many "1s" or "2s" for the five strategies) was
considered in developing the staging program. The result of this
approach is the identification of a high-priority project listing for
facilities under state, county, and local jurisdiction.
High-Priority Projects
High-priority projects have been identified for
roadway facilities under state, county, and local jurisdiction. These
projects satisfy the five strategies to a large extent and were
determined to be needed in the near term to mitigate existing traffic
congestion.
State Roadway Facilities
IL 59 (SRA) widening
U.S. Route 30 (SRA) widening
U.S. Route 30 widening (I-80 to Kane County
line)
IL 53 widening (Boughton Road to Lily Cache
Lane)
IL 53 widening (I-55 to Ruby Street)
IL 171 widening
159th Street widening (Farrel Road to Cedar
Road)
New Des Plaines River bridge at Caton Farm
Road with connection to Bruce Road
New I-80 interchange at Wolf Road
New I-57 interchange at Stuenkel Road with
Stuenkel Road widening (IL 43 to Steger-Monee Road)
Upgraded I-55 interchange at IL 126
County Roadway Facilities
Boughton Road (SRA) widening
Bell Road (SRA) widening
191st Street widening (80th Avenue to IL 43)
Weber Road (SRA) realignment at Naperville
Road
Plainfield-Naperville Road widening (95th
Street to 111th Street)
Caton Farm Road (SRA) widening
Local Roadway Facilities
143rd Street extension (IL 59 to IL 126) and
widening (IL 59 to U.S. Route 30)
88th Avenue extension (U.S. Route 30 to St.
Francis Road)
North Avenue extension (84th Avenue to 88th
Avenue extension)
95th Street extension (Plainfield-Naperville
Road to Boughton Road)
Kings Road extension (Boughton Road to
Ferguson Road)
191st Street widening (Wolf Road to U.S.
Route 45)
135th Street (Romeoville Road) widening
Further study should be completed to develop a
more detailed staging program, with projects separated into a
near-term, mid-range, and long-range timeline based on the estimated
financial resources available. This staging program must consider the
goals and objectives of the plan, transportation needs to be served,
and a realistic time frame for implementation of the major roadway
improvements. The staging program in this plan is simply an attempt to
match transportation infrastructure needs to the available funding at
the state, county, and local levels, and identify the higher priority
projects for near-term implementation so that appropriate engineering
feasibility and environmental studies can be initiated. Considerable
public opposition may significantly delay a project, result in legal
action, or even remove it from future consideration. This aspect of a
project can be difficult to estimate.
Financial Resources and Roadway Capital Costs
A critical requirement for the long-range
transportation plan is that it must be financially attainable. For
this reason, possible financial resources have been inventoried to
identify the order of magnitude of funds that might be used to support
an improvement program. In addition, existing state, county, and local
funding levels have been projected into the future and compared with
the estimated costs needed to finance the roadway elements of the
transportation plan. This study has not attempted to estimate funding
for the transit elements of the plan associated with long-range plans
and programmatic improvements proposed by Metra and Pace. Costs
associated with non-motorized travel paths and trails have also not
been estimated in this plan, as these projects are seen as more
locally developed initiatives.
Possible Funding Sources
Funding for major roadway or transit
improvements comes from a wide variety of sources. Potential sources
are listed below in alphabetical order.
Bridge Tax.
Real estate tax providing funds for county highway bridges.
Congestion Mitigation and Air Quality (CMAQ)
Program. Funding authorized by the
federal government to improve air quality through congestion
mitigation using traffic signal optimization and other roadway
improvements. This funding applies to projects in air quality
nonattainment areas that reduce transportation-related emissions and
improve a metropolitan area's ability to reach National Ambient Air
Quality standards.
Community Development Block Grant (CDBG).
Authorized through the U.S. Department of Housing and Urban
Development (HUD).
FTA Formula Funds.
Funding awarded by the Federal Transit Authority for urban public
transit capital improvement projects and operational assistance
(Section 5307); programs include fixed guideway modernization,
discretionary bus projects, and capital costs of new starts (Section
5309), and the purchase of specially equipped vehicles to transport
elderly or mobility-limited persons.
Gary-Chicago-Milwaukee (GCM) Corridor
Program. Funding provided to
implement intelligent transportation system (ITS) projects in the
corridor.
General Obligation Bonds (GOB).
Bonds authorized through general purpose units of government for
capital improvements.
Highway Bridge Replacement and Rehabilitation
Program (Bridge Funds). Funding
authorized through the U.S. Department of Transportation and TEA-21
for bridge improvements. Bridge funds are allocated to the states on
a formula basis.
Discretionary Bridge Funds.
Funding provided for bridge projects that are not specifically
allocated to the states.
Illinois Commerce Commission (ICC).
Funds authorized for railroad crossing improvements.
Illinois State Toll Highway Authority (ISTHA).
Funding for improvements to I-355 and other toll highways under the
jurisdiction of ISTHA.
Impact Fees.
Funds derived from private new development based on a formula
relating trip generation to road needs.
Interstate Maintenance Program.
Funding provided for the rehabilitation of the interstate highway
system. Funds cannot be used to expand the capacity of the highway;
however, high-occupancy vehicle (HOV) lanes and auxiliary lane
projects are eligible.
Interstate Discretionary Program.
Funds for interstate projects that are not distributed on a formula
basis to the states.
Local. Funding
from unspecified local funding sources, usually from the
jurisdiction's general fund; also includes Township Road and Bridge
Funds and other special funds of local origin.
Matching Tax.
Real estate based tax providing funds for transportation
improvements.
Motor Fuel Tax (MFT).
Taxes on gasoline and fuel oil to be used by the state or local
governments for roadway improvements. This is also the source for
State Bridge Funds.
MFT/County Option.
An additional per gallon fuel tax authorized by a county. Will
County has not legislated the county option MFT as other area
counties have, such as McHenry County (an additional two cents per
gallon tax).
National Highway System (NHS).
A special category of federal funding authorized through TEA-21 for
improvements to the interstate and Strategic Regional Arterial (SRA)
systems.
Operation GreenLight.
State funds aimed at ameliorating congestion on the Strategic
Regional Arterial network. Operation GreenLight transit funds
finance transit-related congestion mitigation programs, including
traffic signal preemption, improved commuter rail station parking
and access, and rail grade crossing improvements.
Private.
Funding committed toward a project from a private landowner or
developer.
Property Tax.
Locally authorized property tax revenues.
Special Assessment (SA).
Special property taxes, assessed and assigned for a specific
improvement.
State. Funding
from the general funds of the State of Illinois.
Special Purpose Authority.
Authorized bonding for improvements.
Surface Transportation Program (STP).
Funding authorized through TEA-21 and administered by the U.S.
Department of Transportation. STP funds can be used for all
classifications of roadways (except local and rural minor
collectors), bridge projects on public roads, and transit capital
projects.
STP High-Priority Projects.
STP funds allocated for specific projects that provide congestion
relief, enhance urban access and mobility, or demonstrate innovation
in highway construction or financing techniques.
STP-Enhancement.
STP funds earmarked for qualified projects that enhance the beauty
of a roadway project, improve non-motorized transportation
opportunities, mitigate the adverse impacts of more traditional
roadway projects, or for other qualified projects.
STP Safety Funds.
STP funds allocated specifically for qualified projects that improve
safety.
STP-Rural. STP
funds allocated to counties for rural highways.
STP-State. STP
funds allocated to the State of Illinois for use on state marked or
unmarked routes or other qualified projects at the state's
discretion.
STP-Urban. STP
funds allocated for use on qualified projects at the discretion of
the metropolitan planning organization (MPO).
Tax Increment Financing (TIF).
Special bonding authority for designated TIF areas/projects.
Projected Funding Levels
The county currently has four sources of revenue
available for the maintenance and construction of highway
improvements. These sources were at the following approximate levels
in 1998.
| Revenue |
Source |
1998
Amount |
| Motor
Fuel Tax (MFT) |
County's
Share of State Gas Tax |
$5,800,000 |
| Matching
Fund |
County
Real Estate Tax |
4,000,000 |
| Bridge
Tax |
County
Real Estate Tax |
3,000,000 |
| Highway
Tax |
County
Real Estate Tax |
4,700,000 |
| Total |
|
$17,500,000 |
From these sources, 100 percent of the highway
tax and approximately 40 percent of the motor fuel tax are allocated
to Highway Department overhead costs. Approximately 40 percent of the
remaining funds must then be allocated to rehabilitation, safety, and
operational projects in order to properly maintain the existing
infrastructure on the county highway system. This leaves an annual
budget of approximately $6.3 million for new roadway construction.
The revenues available to the county are assumed
to increase over time. Motor fuel tax revenues are assumed to increase
at an annual rate of three percent, and real estate tax revenues are
assumed to increase annually at a rate of three percent. Using these
growth rates, the total funding available to the county during the
20-year period (2000 to 2020) would be as follows:
| Revenue |
Source |
2000-2020
Estimated Total |
| Motor
Fuel Tax (MFT) |
County's
Share of State Gas Tax |
$166,300,000 |
| Matching
Tax |
County
Real Estate Tax |
121,700,000 |
| Bridge
Tax |
County
Real Estate Tax |
91,300,000 |
| Highway
Tax |
County
Real Estate Tax |
143,000,000 |
| |
Gross Total |
522,300,000 |
| Highway
Dept Overhead |
(100% of highway
tax, 40% MFT) |
(209,520,000) |
| |
Subtotal |
312,780,000 |
| Safety/Rehab/Operations |
(40% of subtotal) |
(125,110,000) |
| |
Net Total
Available |
$187,670,000 |
These funds would be applied to the county's
share of the total transportation improvement program. Additional
highway funding for the state, tollway, and municipal shares of the
program would originate from other sources. Federal transit funds,
state motor fuel tax (Operation GreenLight) and RTA sales tax are used
by the RTA and its service boards (Pace, Metra, CTA) and the IDOT
Division of Public Transportation to fund public transportation
services in northeastern Illinois. Other grant-style federal programs
exist, such as the STP enhancement program, and are tailored to a
specific type of improvement.
Capital Costs for Roadway Elements
For the roadway projects included in the plan,
the estimated capital cost is approximately $1.03 billion without
improvements by the Illinois State Toll Highway Authority (ISTHA). If
the tollway improvements, including the I-355 extension from I-80 to
I-57, are added, the total cost rises to $1.9 billion. If a third
regional airport is developed in the Peotone area, additional roadway
projects that would need to be implemented to support the airport
would increase the capital cost for the plan to $1.26 billion, without
the ISTHA tollway improvements, and $2.5 billion with the tollway
extended farther east to IL 394.
The plan recommends several roadway and
intersection realignments that would extend into Cook, Kendall, and
Kankakee Counties and Lake County in Indiana. Because the cost of
these projects would be funded at least partially by these respective
counties or other agencies, for planning purposes, these project costs
were not included in Table 19 and Table
20.
Agency Funding of Plan
Many of the recommended improvements projects
will have cost participation by more than one agency. For planning
purposes, the project costs were assumed to be borne by the agency
that has jurisdiction over the facility. As indicated in Tables 19 and
20, the Illinois Department of Transportation (IDOT) would share the
burden of funding, with approximately $642 million (63 percent,
excluding ISTHA projects) ($835 million with the third airport) worth
of improvements. While the county has little control over the level of
IDOT funding in Will County, a review of IDOT's previous programs has
indicated an investment of approximately $26 million per year
(including rehabilitation funding), or $520 million over the proposed
20-year planning period. As can be seen, while the program is within
reach, the cost of rehabilitation funding will result in a shortfall
for new construction projects.
The $218 billion, six-year TEA-21 federal
transportation legislation and $12 billion, five-year Illinois FIRST
state public works program will provide more funds for transportation
projects than were available in the past. The five-year transportation
budget for IDOT represents a 50 percent increase over existing
programming capacity. Although the transportation plan for the state
highway system in Will County may still be unfundable in its entirety,
it can serve as a preferred needs list as to where state and federal
level investment dollars could be directed in Will County.
As mentioned previously, it is estimated that
the county will have available approximately $188 million for capacity
improvements over the next 20 years. With the county's estimated share
totaling $197 million (19 percent, excluding ISTHA projects), the
proposed county highway portion of the program would be potentially
attainable, if, recognizing the rapid growth occurring in the county,
a larger allocation of the state MFT were allocated to Will County and
other (possible new) funding sources were developed.
If a third regional airport is developed in the
county, the county's share is estimated to cost $255 million.
Reductions in the estimated cost of some projects, elimination of four
or five projects that may not be as high a priority if new development
is focused more on the eastern end of the county, or an increase in
federal Surface Transportation Program (STP) funds could result in a
"balanced" program. Therefore, the county's program over the
next 20 years appears financially feasible, provided that funding
continues at the levels estimated above or increases.
Approximately 9 percent of the total program
($92.8 million) has been allocated to local funding. This share could
also be reduced by increased developer participation, or through an
effort by the Will County Governmental League to fund some of these
projects. Municipalities presently have the authority to negotiate and
levy impact fees that can be used to defray the high cost of
infrastructure improvements. In addition, the Will County Governmental
League is currently allocated approximately $1.7 million per year in
federal (STP) funding. Therefore, over the 20-year planning period,
approximately $34 million could be available for county- and
municipal-funded projects if STP funding remains at its present level.
Similarly, funding for the transportation
planning initiatives could also be secured through regional and
federal grant programs. The estimated cost of these initiatives would
be rather small when compared to roadway construction costs. Because
the scope of these planning studies has not been determined, a cost
estimate has not been developed.
Recommended New Funding Sources for County
Roadway Improvements
Beyond the funding sources that have recently
been used to support infrastructure improvements in Will County,
growth projections indicate a clear need for increased transportation
funding at the federal, state, and local levels. Potential new or
increased funding could come from the following sources:
- STP High Priority Projects.
This federal program provides funding for projects that relieve
congestion, enhance urban access and mobility, and demonstrate
innovative techniques in highway construction or financing.
- County Option Motor Fuel Tax.
The county potentially has the legislative authority to enact a
local gas tax that would provide additional funds for roadway
projects. DuPage, Kane, Cook, and McHenry counties have all
authorized this additional gas tax. McHenry County, as an example,
has authorized an additional two-cent per gallon fuel tax, with
legislative authority to increase the tax up to four cents per
gallon. Will county must either first convince state lawmakers to
grant it the authority to do so, or county residents must vote to
approve home rule authority, which would give the County Board
authority to implement a gas tax on its own. Will County and Lake
County are presently the only counties in the NIPC six-county region
that have not been given state authority to levy a gas tax.
- Transportation Impact Fees.
The county currently has the legislative authority, which requires a
population of 400,000 more, to collect impact fees as Lake County
currently does. The county would assess impact fees on private
developments to provide roadway improvements based on a developed
formula that could potentially consider the traffic impact of the
proposed land use, capacity of impacted facilities, road improvement
costs, and tax credits. The county would first need to develop an
impact fee ordinance to govern the fees.
- Tax Increment Financing (TIF).
Local municipalities can authorize TIF districts to channel tax
revenues directly back into infrastructure redevelopment within
their communities.
Funding for public transportation improvements
would come primarily from federal transit funds (Federal Operating
Assistance Fund and Operation GreenLight Fund) and RTA sales tax
receipts and would then be distributed to Metra and Pace. Additional
state subsidies are available through the IDOT Department of Public
Transportation (Public Transportation Fund). It is anticipated that
proposals for new commuter rail stations, increased service, and
commuter rail extensions would be developed as part of the RTA's
overall long-range planning process.
Additional multimodal improvements that are part
of a roadway project (such as park-n-ride lots, high-occupancy vehicle
lanes, bicycle lanes, etc.) would also be funded through federal
programs targeted to support such measures, or added to the roadway
cost as part of an individual project.
Federal STP enhancement funding could be used in
the future for bikeway/pedestrian projects if the enhancement program
is reauthorized by Congress.
Implementation Process
Transportation improvements are implemented on
various levels in northeastern Illinois:
- Regional level.
Federal funds for transportation projects are distributed and
administered through several Federal Transit Administration (FTA)
and Federal Highway Administration (FHWA) programs through the
Metropolitan Planning Organization (MPO) process. The MPO for Will
County is the Chicago Area Transportation Study (CATS), which
programs improvements for the six northeastern Illinois counties
through the development and adoption of a Transportation Improvement
Program (TIP). CATS carefully considers input from local governments
and long-range plans such as this one. Proposed improvements that
will be implemented in the next year and within the next three years
are developed by the Work Program Committee and the Policy Committee
of the MPO. Will County is represented on these committees. Proper
notices are made advising the public of the proposed TIP, and
required public hearings are held to obtain citizen input. The TIP
is published as a separate document by CATS. It is updated and
republished each year.
- Additional regional transit improvements are
implemented directly through the Regional Transit Authority and
its service boards (Metra, Pace, CTA). RTA and service board
funding comes from federal, state, and local sources, as well as
through direct farebox revenues.
- County level.
In Will County, the Will County Highway Department is responsible
for the maintenance and new construction of county roadways and
bridges. Projects identified by the highway department are submitted
to the County Board Public Works Committee for review and eventual
incorporation into the annual Capital Improvement Plan for Will
County, which is adopted by the full county board. County projects
are funded primarily by state and county revenue sources.
- Local level.
Local projects include those funded by the municipal governments and
townships through local real estate taxes and motor fuel tax
revenues. These projects are approved and funds appropriated by city
councils, village boards of trustees, or township trustees on the
recommendations of the resident engineer representing the local
community.
Conclusion
From a planning standpoint, the recommended plan
appears to be financially attainable for the county highway system and
can be implemented in the next 20 years, with some project
construction extending beyond this time frame. Detailed funding
estimates were prepared for county funding, while the estimate of
state funding was based on historical levels. In both cases, new
revenue sources or increased funding for transportation improvements
will be critical if the transportation infrastructure is to keep pace
with rapid development growth and associated travel demand projected
for Will County's roadway system. The burden of the local share of
improvements can be attained through successful cooperation with the
development community and the use of outside funding, such as STP
funds distributed through the Will County Governmental League.
The plan has also identified higher-priority
projects. In this way, the various roadway agencies could assess the
relative importance of the projects and schedule their planning,
engineering, and construction as growth takes place and the need for
the facility is warranted. It would also establish a prioritization of
the projects to be included in the regional Transportation Improvement
Program (TIP).
New roadway construction, however, is becoming
increasingly difficult to accomplish. Even the simplest projects are
often met with extremely vocal opposition from local residents. Land
acquisition can take up to five years, and most environmental studies
for new facilities take at least one year. Therefore, major roadway
expansion projects such as IL 59 have a realistic timeline of 10
years. Today, new roadway projects require environmental, historical,
archaeological, air quality, and cost-analysis studies before even
proceeding to the engineering stage. While the public may not feel
that this is an acceptable time frame to accomplish these
improvements, it is a realistic one within the current regulatory
structure. In order to condense this time frame further, legislative
action on the state and federal levels will be necessary to help
streamline the process.
This plan develops the county strategy to guide
future development. It serves as the overall plan of the county and
its municipalities. The plan summarizes most of the plans and
documents previously developed by the MPO, IDOT, county, and municipal
governments. As new updated plans are developed, their findings and
recommendations should be incorporated into this document.
The plan is one step in a continuous ongoing
process. The policies and strategies outlined in this document will be
continually refined and improved over time. The efforts of all people
and leaders in the MPO and county are required to further improve the
region and the various elements of the transportation system.
Click here to view Table
19 and Table 20